5.2Consultation
5.3Procurement
5.4Construction
5.5Commissioning,OperationandMaintenance
6.ProjectControls
6.1ChangeControl
6.2Programme
6.3Cost
6.3.1CostPlanning
6.3.2CostReporting
6.3.3InvoicingProcedure
6.3.4Risk
6.4Quality
6.4.1Definitionofstandards
6.4.2SiteControlsandInspection
6.4.3DefectsRectification
6.5OrganisationandAdministration
6.5.1ProjectFilingSystem
6.5.2Meetings
6.5.3ProjectProgressReporting
6.6HealthandSafet
Thepurposeofthisdocumentistodefineallproceduralmattersrelatingtothedesign,procurementandconstructionoftheproject.ThisdocumentshouldbereadinconjunctionwiththeUniversityofLeedsProjectManagerHandbook.
TheProjectExecutionPlan(PEP)ispreparedbytheProjectManagerinconsultationwiththeclientandtheProjectteam.Itdescribesthegeneralprocedurestobeadoptedbytheclientandtheteamfortheproject.
ThePEPisnotastaticdocument.Itshouldberegularlyupdatedbyeachteammember,althoughallrevisionswillbeissuedthroughtheProjectManagertoretainanelementofcontrol.
TheobjectivesofthePEParetoachievetheclient’srequirementsintermsoftime,costandqualityvia:
∙GuidingtheProjectteammembersintheperformanceoftheirduties
∙Monitoringandcontrollingprojectprogrammeanddelivery
∙Maintaininganadequateandtimelyflowofcriticalinformation
Thedocumentissplitintothefollowingsections;
1.TheUniversityofLeedsProjectManagerHandbook
2.Projectobjectivesandpriorities
3.Organisation,rolesandresponsibilities
4.Projectstrategy
5.Projectcontrols
TheUniversityundertakesawiderangeofmaintenanceandnewbuildprojectsandhasdevelopeda
UniversityofLeedsProjectManagerHandbookforuseon
Universityconstruction
projects.Ateachstageoftheprojectthehandbookshouldbereferredtoforguidanceandsupport.Withinthehandbookisaseriesofprocesseswhicharesupportedbyarangeofproceduresandtemplates.Eachprojectalsohasasetofeightgatewayreviewsthatmustbesignedoffbytherelevantpartiesbeforeaprojectcanproceedtothenextstage.
ProjectProcesses
Theprocesseshavebeendevelopedtocoverthetasksthatareundertakenduringeachofthesixprojectlifecyclestages:
FeasibilityOptionAppraisal(RIBAStageA/B)
OutlineProposals(RIBAStagesC)
DetailProposals(RIBAStagesD,E)
Tender(RIBAStagesF,H)
Construction(RIBAStagesJ,K)
PostProject(RIBAStageL)
3.ProjectObjectivesandPriorities
Client’sbriefanddesigncriteria
Summaryofprojectaims
Summaryoflocation,generalarrangementsandanysiteconstraints
ApprovalStage
ApprovalSignoffDate
Gateway1Approval–PrimaFacieBusinesscaseSignoff
Gateway2Approval–FullBusinessCaseSignoff
Gateway3Approval–FundingGranted
Gateway4Approval–StageA/BSignOff
Gateway5Approval–StageCSignOff
Gateway6Approval–StageD/EsignOff
Gateway7Approval–TenderReportApproval
Gateway8Approval-Completion
CurrentApprovedProgramme
Location:
CurrentApprovedBudget
4Organisation,RolesandResponsibilities
Thenames,address,telephonedetailsofalltheorganisationsinvolvedintheprojectareincludedwithintheprojectdirectory.(ReferenceTemplate–ProjectDirectory)
4.2KeyContacts
TheProjectTeam
Theprinciplepartiesinvolvedwiththeprojectare:
ClientLiaisonOfficer:
Mobile
Email
EstatesProjectManager:
Mobile
ExternalProjectManager:
QuantitySurveyor:
Mobile
Tel
Architect:
M&
EServicesEngineer:
StructuralEngineer:
Mobile
CDMConsultant:
MainContractor:
4.3DesignTeamTendersReceivedandAccepted:
Required
Received
Action
ProjectManager
Architect
EEngineer
S&
CEngineer
QuantitySurveyor
CDMCo-ordinator
4.4AgreeDesignTeamFeeScheduleandDrawdown:
4.5ExecuteDesignTeamAppointmentDocumentation:
4.6ExecuteandIssueDesignTeamProfessionalWarranties:
4.7ExecuteandIssueDesignTeamNovationAgreement:
4.8ConstructionContractParticulars
ContractNoticeIssue
PQQ
PQQEvaluation
ITT
ITTEvaluation
TenderReport
Executeandissuemaincontract
5.0ProjectStrategy
TheUniversityhasdeterminedastrategythatwillbeadoptedoneachprojectforthemanagementofdesign,procurement,constructionandcommissioning,OperationandMaintenance.
ThedesignteamwillbemanagedbytheArchitectasleadconsultant.RolesandResponsibilitiesaredetailedwithinthefollowingtemplates;
-ScopeofService–ExternalProjectManager
-ScopeofService–Architect
-ScopeofService–MechanicalandElectrical
-ScopeofService–StructuralandCivil
-ScopeofService–QuantitySurveyor
-ScopeofService–CDMC&
SWMP
-ScopeofService–BREEAMAssessor
-ScopeofService–Acoustics
-ScopeofService–FireEngineer
-ScopeofService–MonitoringArchitect
ConsultantDesignResponsibilityMatrix
Reference:
Date:
1=PRIMARYRESPONSIBILITY
2=SUPPORTINGROLE
IfthereisnoExternalProjectManager,theEstatesProjectManagerwillundertakeallthedetailedresponsibilities.
ExternalProjectManager
Civil/StructuralEng
Mechanical&
ElectricalEng
CDMCoordinator
MainContractor
AppointmentofConsultants
1
2
BriefInformation
Instructchangestobrief
Designteamco-ordination
Co-ordinationofservices
Siteownershipandboundaries
Landand/orbuildingsurvey
Servicessurvey
Adjoiningpremises/department
Airand/orwatercondition
PlanningApplication
BuildingRegsComplianceCertificate
FireCertificateApplication
WaterretainingtankingDPC’sandDPM’s(roof)
Buildingenvelopedesign
Internalwalls,partitions,ceilings
Internalfinishes
Buildingstructureelements
Paintperformancespectoprimarysteel
Galvperfspectoexternalsteel
Subcontractordesigncriteriaforconcealedsteelworkconnections
Architecturalmetalwork
Undergrounddrainage
Roofdrainage
Intdrainage
Intsanitaryinstallation
Sanitaryfittings
Rainwatersystem
Mainwatersupply
Coldwaterdistribution
Hotwatersupply/distribution
Structurefireprotectionperformancespecforintumescentpaint
Firestopping
Firefightinginstallationsandstrategy
Firealarm/detection
Electricalpowerandlighting(InternalandExternal)
Communicationssystems
Securityservices
BMSSystems
Lightningprotection(earthingandbonding)
Heatinginstallation/fuelsupply
Buildersworkholes>
150mmx150sq
Buildersworkholes<
150x150
Mechanicalengineering
Plantroomlayouts
Airconditioningsystems
Maingassupply/distribution
Lifts,conveyorsandhoists
Refrigerationplant/installations
ExternalEnvelopeCleaningandMaintenance
LaboratoryEquipment
SpecialistEquipmentschedule
Labfurniture
Servicessoundcontrolandacoustics
AVSystems
Videoconferencingservices
Fixedfurnitureandfittings(notloose)
Signage
Hardandsoftlands