高层悬挑脚手架工程施工设计方案29108文档格式.docx
《高层悬挑脚手架工程施工设计方案29108文档格式.docx》由会员分享,可在线阅读,更多相关《高层悬挑脚手架工程施工设计方案29108文档格式.docx(16页珍藏版)》请在冰豆网上搜索。
案
编制单位:
成都盛兴建设有限公司
编制日期:
二〇一〇年八月六日
1编制依据..................................................................................1
1.1主要规程、规范..........................................................................1
1参考手册...................................................................................1
2工程概况.......................................................................................1
2.1总体工程概况................................................................................1
.2脚手架工程概况..........................................................................1
3施工部署..............................................................................................1
3.1安全防护领导小组..................................................................1
3.2设计总体思路.....................................................................................1
4构造要求及技术措施...........................................................................2
4.1扣件式钢管脚手架的构造要求及技术措施.........................….2
4.1.1地基处理........................................................................…..2
4.1.2立杆..........................................................................................…..2
4.1.3大横杆........................................................................................…..2
4.1.4小横杆..............................................................................…..2
4.1.5纵、横向扫地杆...................................................................…..2
4.1.6剪刀撑.......................................................................................…..2
4.1.7脚手板.............................................................................…..2
4.1.8连墙件................................................................................…..3
4.1.9防护设施..............................................................................…...3
4.2转料平台..........................................................................................3
4.3脚手架出入口的构造..............................................................3
5安全防护措施.......................................................................................3
5.1电梯井洞口防护措施.............................................................3
5.2结构临边防护措施..................................................................…3
5.3楼梯间防护措施...................................................................…4
6脚手架的搭设及拆除施工工艺......................................................…4
6.1落地式钢管脚手架搭设施工工艺………………………………4
6.2悬挑式钢管脚手架的搭设施工工艺...............................................4
6.3转料平台的施工工艺..................................................................…4
6.4脚手架的拆除施工工艺....................................................................5
7劳动力配备…………………………………………………………..5
8质量保证..........................................................................................…5
8.1构配件允许偏差.............................................................................…5
8.2脚手架搭设的允许偏差和检验方法.............................................…5
8.3扣件拧紧抽样检查数目及质量判定标准...................................5
8.4质量保证注意事项.................................................................…6
9安全施工措施................................................................................6
9.1材质及其使用的安全技术措施...............................................….6
9.2脚手架搭设的安全技术措施........................................................6
9.3脚手架上施工作业的安全技术措施................................................6
9.4脚手架拆除的安全技术措施..........................................................7
10文明施工要求.......................................................................7
11脚手架稳定计算.................................................................9
11.1外双排脚手架计算依据..............................................................9
11.1.1钢管截面特征................................................................……9
11.1.2脚手架特征参数.............................................................……9
11.1.3相关计算参数....................................................................……9
11.2外双排脚手架验算………………………………………………10
11.2.1荷载计算…………………………………………………….10
11.2.2脚手架整体验算…………………………………………….10
11.3悬挑式脚手架的设计计算.........................................……..11
1编制依据
1.1主要规程、规范
1.1.1JGJ130-2001建筑施工扣件式钢管脚手架安全技术规范
1.1.2JGJ80-91建筑施工高处作业安全技术规范
1.1.3JGJ59-99建筑施工安全检查标准
1.2参考手册
1.2.1《建筑施工手册》(第4版)
1.2.2《简明施工计算手册》(1999.7)
1.2.3建筑施工扣件式钢管脚手架构造与计算
2工程概况
2.1总体工程概况
2.2脚手架工程概况
屋面结构顶标高21.6m,地下室至结构二层采用双排落地外架,从二层板顶(标高4.5m)开始安装悬挑外架,五层一挑共挑五次至顶层。
3施工部署
3.1安全防护领导小组
安全生产、文明施工是企业生存与发展的前提条件,是达到“无重大伤亡及消防、机械事故,一般事故频率控制在3‰以内”安全生产目标的必然保障,也是我项目部创建市级文明工地的根本要求。
为此项目经理部成立以项目经理为组长的安全防护领导小组,其机构组成、人员编制及责任分工如下:
组长:
——负责协调工作
副组长:
——现场施工总指挥
——技术总指导
组员:
——现场施工协调
——现场施工组织
——现场安全检查、验收
3.2外架设计总体思路
结合本工程结构形式、实际施工特点,脚手架施工及使用划分为二个阶段:
地下室外墙及二层结构施工阶段:
依据基坑工作面情况决定使用落地双排脚手架,脚手架立杆距离结构墙面30cm。
立杆纵距1500mm,横距1000mm,步距1500mm。
基础一次处理好,保证外架搭设符合要求。
地上2~6层结构及装修施工阶段:
从三层结构板面开始安装悬挑钢梁,采用悬挑外脚手