资源描述

知名地产集团住宅室内装饰施工工艺和质量标准图文并茂word版.docx

《知名地产集团住宅室内装饰施工工艺和质量标准图文并茂word版.docx》由会员分享,可在线阅读,更多相关《知名地产集团住宅室内装饰施工工艺和质量标准图文并茂word版.docx(156页珍藏版)》请在冰豆网上搜索。

知名地产集团住宅室内装饰施工工艺和质量标准图文并茂word版.docx

知名地产集团住宅室内装饰施工工艺和质量标准图文并茂word版

 

第一章住宅室内装修工序间歇及工艺间歇标准······························3

1.1墙面各工序间歇及工艺间歇要求标准···········································3

1.2地面各工序间歇及工艺间歇要求标准············································3

1.3木地板施工基层要求标准································································4

1.4细部处理各工艺间歇要求标准························································4

1.5其它装修施工要求············································································4

第二章住宅室内装修工艺流程标准·····················································5

第三章住宅室内装修施工工艺和质量标准········································6

3.1场地移交····························································································6

3.2弹线···································································································10

3.3电线穿管···························································································14

3.4卧室地面找平···················································································15

3.5墙面砖铺装·······················································································17

3.6墙面石材铺装···················································································23

3.7天花吊顶、石膏线安装·····································································28

3.8入户门安装·······················································································31

3.9地面砖、石材铺贴·············································································34

3.10窗台石铺贴·····················································································40

3.11天花墙面扇灰、涂饰乳胶漆···························································42

3.12墙面造型制作、安装·······································································47

3.13橱柜、卫浴安装················································································51

3.14户内门安装······················································································57

3.15木地板安装······················································································63

3.16墙面玻璃镜面安装·········································································70

3.17墙面木饰面造型油漆·····································································70

3.18墙纸贴铺·························································································73

3.19阳台护栏安装·················································································77

3.20低窗护栏安装·················································································78

3.21墙面软包制作安装·········································································80

3.22灯具、插座开关面板安装·······························································82

3.23卫生洁具安装·················································································97

3.24卫浴五金安装···············································································104

3.25淋浴隔断安装···············································································105

3.26细部处理·······················································································106

3.27石材镜面处理···············································································114

3.28卫生清理·······················································································116

 

恒大地产集团

住宅室内装修施工工艺和质量标准(试行)

施工工序原则:

先上后下、先湿后干、先内后外、先粗后细、先制作后安装。

第一章住宅室内装修工序间歇及工艺间歇标准

1.1墙面各工序间歇及工艺间歇要求标准

≥28天≥28天≥15-20天≥7天

工艺要求工艺要求工艺要求

 

1.2地面各工序间歇及工艺间歇要求标准

1、卧室木地板、地毯等基层地面找平完成后,可上人作业间歇时间为不小于48小时。

2、客厅、餐厅、厨房、卫生间、阳台、电梯前室、首层大堂等地面砖、石材铺贴完成后,可上人作业间歇时间为不小于48小时。

3、室内地面砖、石材及地面找平完成后,墙面1米线以下墙体刮装饰腻子需要间歇不小于15-20天,其要求含水率不大于14﹪。

1.3木地板施工基层要求标准

木地板地面基层含水率标准一览表

地区

季节

春、夏

≤12﹪

≤8﹪

秋、冬

≤8﹪

≤8﹪

1.4细部处理各工艺间歇要求标准

1、厨房、卫生间、阳台、电梯前室、首层大堂等墙面砖采用湿贴工艺,砖缝水泥清理所需间歇时间为3-6小时。

2、墙面、地面、台面等湿贴作业完成后,需钻孔、打眼等间歇时间不小于14天。

3、各交界面细部处理打胶后,与卫生清理间歇时间不小于24小时。

4、入户门门框安装后,门扇安装所需间歇时间不小于72小时;户内门门框安装后,门扇安装所需间歇时间不小于24小时。

1.5其它装修施工要求

1、小高层结构至8层,中高层、高层结构施工至12层,砌体开始施工时,装修施工单位定标、不少于2名装修管理人员到位。

3、外立面装饰完成10层,外脚手架拆除上面5层,且卫生清理完毕,进行场地移交,装修施工人员全部到位。

4、小高层分2批移交,每批5层,移交间歇时间15天;中高层、高层分3批移交,第1批5层,第2、3批移交10层左右,流水施工作业。

第二章住宅室内装修工艺流程标准

 

第三章住宅室内装修施工工艺和质量标准

3.1场地移交

3.1.1室内场地移交

1、室内结构楼板、墙面无穿透性裂缝和渗漏水缺陷。

2、室内天花结构板无下挠,平整度误差不大于8mm,梁底两端高差不超过8mm,模板接缝处应磨平。

3、墙体砌筑、批荡(卫生间、厨房墙面为1:

2水泥砂浆,其余墙面为混合砂浆)完成,基层无空鼓、开裂、起灰等质量缺陷,房间墙面阳角部位需做不低于2米高1:

2水泥砂浆护角,垂直度、平整度误差不大于3mm。

4、铝合金门、窗框安装到位,窗台两端尺寸误差不大于10mm,阴阳角方正偏差不大于4mm,窗框塞缝完毕且淋水试验合格,无窗框渗漏水。

5、厨房、卫生间、阳台等给排水管线预埋及给水管试压合格。

6、厨房烟道安装并挂网批荡,挂网与墙体搭接150mm,防水封堵和止回阀安装完毕且验收合格,烟道排烟口顶至楼板底高度为150mm。

7、强弱电预埋管线、底盒位置与设计图纸一致,管线畅通。

8、隐蔽水电管道位置应标识清楚。

9、高位空调(卧室、书房)套管穿大于或等于700mm高的窗顶梁时,套管孔顶距梁底不大于220mm;穿剪力墙或砌体时套管孔顶距板底不小于400mm,且不大于600mm。

10、地面标高误差控制在±10mm内,平整度偏差不大于8mm,阳

台排水立管封堵和蓄水试验完成,无渗漏水。

11、阳台防水施工完毕且验收合格。

12、户内门洞尺寸满足设计要求,门套两侧及顶部墙体砌筑材料严禁为空心砌块,且厚度误差不大于10mm。

 

无地暖地区户内门洞移交尺寸一览表(单位:

㎜,以结构1米线下935㎜为基准)

型号

建筑门洞尺寸(以地面完成面计算)

建筑门洞结构1米线上高度

建筑门洞宽度范围

门头梁底距结构1米线最小高度

墙体厚度

最大误差

单扇平开房门

850×2200

950×2250

1315±5

950±5

1350±5

10

单扇平开房门900×2400

1000×2450

1515±5

1000±5

1550±5

10

厨房单扇平开门750×2200

850×2250

展开阅读全文