MethodStatement
DocumentTitle:
ConstructionofTrafficDiversionRoads
DocumentNo.:
EXW-P011-0000-CM-CHE-MT-00068-Rev.CD
Name&Signature
Position
Date
PreparedBy:
TechnicalEngineer
ReviewedBy:
TechnicalManager
ApprovedBy:
ProjectManager
RevisionHistory
Revision
Date
Detailsofrevision
CA
27-Apr-2014
Submitforapproval.
CB
28-May-2014
ComplywiththecommentsfromHalcrowdatedon6-May-2014
CC
12-Oct-2014
ComplywiththecommentsfromHalcrowdatedon23-Aug-2014
CD
20-Nov-2014
ComplywiththecommentsfromHalcrowdatedon18-Oct-2014
Section
CONTENTS
Page
1.0
Purpose
3
2.0
ScopeofWork
3
3.0
Responsibilities
3
4.0
PermitsandLicences
3
5.0
SequenceofConstructionofTrafficDiversionRoads
4
6.0
ResourcestobeusedforConstructionofTrafficDiversionRoads
4
6.1Reference
4
6.2Control,Storage&ProtectionofSpecificMaterials
5
7.0
DetailedmethodofCarryingOutthisMethodStatement
5
8.0
QualityControlandRequirements
10
9.0
Health&SafetyConsiderations
10
9.1Generalsafetyissues
10
9.2EmergencyArrangement
11
9.3ConsentsandPermits
11
10.0
EnvironmentalConsiderations
12
10.1EnvironmentalAspects
12
10.2Housekeeping
12
11.0
Appendices
12
AppendixA
-
RiskAssessment
AppendixB
-
ToolBoxTalk
AppendixC
-
InspectionandTestPlan
AppendixD
-
ChecklistForm
Section1.0:
Purpose
Thismethodstatementistodescribetheprocedureandtechniquesofconstructionoftrafficdiversionroadsinasafemannerthatwillsatisfyalltherequirements.
Section2.0:
ScopeofWork
Thismethodstatementdescribestheactivitiesrelatedtotrafficdiversionroads,includingsiteclearance(REF:
EXW-P011-0000-CM-CHE-MT-00002),embankment(REF:
EXW-P011-0000-CM-CHE-MT-00011、EXW-P011-0000-CM-CHE-MT-00006),sub-grade(REF:
EXW-P011-0000-CM-CHE-MT-00011、EXW-P011-0000-CM-CHE-MT-00006),roadbase(REF:
EXW-P011-0000-CM-CHE-MT-00025),asphaltwork,installationofpolelight(REF:
EXW-P011-0000-CM-CHE-MT-00085),trafficsignal(REF:
EXW-P011-0000-CM-CHE-MT-00096),installationofsignboard,safetybarriersandroadmarkingetc.Theseactivitiesarecoveredinseparatedmethodstatement.
Section3.0:
Responsibilities
TheworkwillbecarriedoutbyCHEC,headedbytheConstructionManager.
•ConstructionManager–Partiallyresponsiblefortheconstructionandarrangementofcivilworks,inchargeofsiteengineer.
•HSEEngineer&HSEOfficer–ResponsibleforHSEonsiteduringconstruction,coordinatewithSiteEngineer,infrastructuresuperintendent.
•QCEngineer–Responsibleforqualityofstructureonsiteduringconstruction,coordinatewithSiteEngineer,requestforInspectionandTestingprocessesandcoordinationwiththeEngineer’sInspectorsrepresentative.
•Surveyor–Responsibleforsurveyworkandsettlementmonitoringworkonsite,coordinatewithSiteEngineer,thesurveyrequestprocessandcoordinationwiththeEngineer’ssurveyorrepresentative.
•SiteEngineer–Siteengineerresponsibleforconstructionofwork,coordinatewithHSEEngineer,QA/QCengineer,surveyor,willinchargeofforemen,operators,drivers,labours,reportsdirectlytoconstructionmanager,requestforInspectionandTestingprocessesandcoordinationwiththeEngineer’sInspectorsrepresentative,aswellassupervisor.
•Foreman-Directlysupervisestheworkactivityonthesiteandhasfullcontrolovertheuseofthelabour,plantandequipment.Heensuresthattheworkiscarriedoutinfullcompliancewiththespecification,andinamannerthatconformstothesafetyrequirements.HereportstotheSiteEngineerwhentheworkiscompleteandreadyforinspection.
•Allpersonnel(operators)shouldbequalifiedandtherelevantcertificateshouldbeavailable.
Section4.0:
PermitsandLicences
Whererequiredasperprojectcontractspecification,permits&licencesshallbeobtainedfromrelevantauthoritiespriortostartwiththerelatedworksoractivities.
Section5.0:
SequenceofConstructionofTrafficDiversionRoads
Thesequenceoftrafficdiversionroadsasshowninthefollowingchart:
SequenceofTrafficDiversionRoads
Section6.0:
ResourcestobeUsedforConstructionofTrafficDiversionRoads
6.1References
•QCS2010
•HSEplan&ProjectqualityplanapprovedbySC.
•MethodstatementswhichhavebeenapprovedbyEngineer:
Methodstatementofengineeringsurvey:
EXW-P011-0000-CM-CHE-MT-00001.
Methodstatementofsitedemolitionandclearance:
EXW-P011-0000-CM-CHE-MT-
00002
Methodstatementofsoilfillingandcompactionforroadworks:
EXW-P011-0000-CM-CHE-MT-00011
Methodstatementofaggregateroadbaseandsub-base:
EXW-P011-0000-CM-CHE-MT-00025
•ApprovedBCType-1andSCType-1designmixes.
6.2Control,Storage&ProtectionofSpecificMaterials
•Materialsshallbestoredandhandledastoassurethepreservationoftheirqualityandfitnessforuseintheworks.Evenaftersourceapprovalhasbeengivenmaterialsmayagainbeinspectedandtestedbeforeusedinthework.
•Eachshipmentofmaterialsisloaded,shouldbeblockedandsecurelyfastentoavoiddamagesduringtransportation.
•Theimportantmaterialsshouldbekeptcleanawayfromoil,grease,excessiveheatandoutofthedirectraysofthesun.
•CHECshalltakeallnecessaryprotectionmeasuresinthestorage,handlingandstockpilingofmaterialstopreventcontaminationofmaterialbytest.
Section7.0:
DetailedMethodofCarryingOutthisMethodStatement
7.1Preparationpriortowork
•Allequipmentsaretestedandsuitableforthecurrentwork.
•Alltheequipment,material,andpersonnelstaffhavebeenpreparedinsitu.
•Alltheequipmentsarefunctioningalltime.
•Electricalpowerwillbemainlysuppliedbygenerators.Thegeneratorswillbeavailableandplacedclosetotheworkingarea.
7.2Permitshallbeobtainedbeforecommenceofwork
•AllmaterialsandmixdesignsshallbeapprovedbyEngineerpriortouseinconstruction.
•AllnecessaryWorkpermitsshallbeobtainedpriortothecommencementofanyactivityonthesite.PersonnelresponsibleforsupervisingtheWorksonsite(Engineers/Forman)shallbeawareofthepermittoworksystemandpermitshallbevalidthroughouttheentiredurationoftheoperation.
•AllequipmenttobeutilizedonsiteshallhaveavalidThirdPartyCertificate.
•Competentpersonnelshallberesponsibleforliftingactivities.
7.3Checkingofundergroundutilities
•Priortocommenceofworks,undergroundutilitiesshallbecheckingaccordingtoas-built,undergrounddetectingreportsetc.
•Ifthereisanyundergroundutilityindesignedarea,propermethodshallbeimplementedtoprotecttheutility.
•Workpermitshallbegivenbyspecificauthoritypriortoworkifanyundergroundutilitycouldhavebeenfoundonworksite.
7.4SiteDemolitionandClearance
•Refertothelatestmethodstatementofsitedemolitionandclearance(documentno.:
EXW-P011-0000-CM-CHE-MT-00002).
7.5SoilFillingandCompactionforRoadWorks
•Refertothelatestmethodstatementofsoilfillingandcompactionforroadworks(documentno.:
EXW-P011-0000-CM-CHE-MT-00011).
7.6Aggregateroadbase
•Refertothelatestmethodstatementofaggregateroadbaseandsub-base(documentno.:
EXW-P011-0000-CM-CHE-MT-00025).
7.7Asphaltwork
7.7.1SupplyandSprayofPrimeCoat:
Priortolayoftheasphaltmix,primecoatofMC-70mediumcuringcutbackasphaltwillbeappliedtoanabsorbentroadbasesurfacewhichwillprepareatreatedbaseasperQCS2010,Clause5.12insection6.ThePrimecoatpenetratesintothebaseandplugsthevoidsandhardensthetopandhelpshindittolayittotheoverlayingasphaltcourse.Applicationofprimecoatwillbeasfollows:
•Primecoatwillbesprayedoverthepreparedroadbase.
•Theapplicationratewillbebetween0.75and1.00lit/Sqm.andtheapplicationtemperaturewillbebetween60oCdegreeand85oCdegree.
•Theprimecoatwillbecutbackbitumenconsistingofa60/70penetrationgradebitumenandkerosene.Theresiduefromthedistillationtest,carriedoutto360oC,shallbeaminimumof55%(byvolume),asdeterminedbythedifferencemethod.
•Ifthesurfaceiscoveredinwind-blowndustorfineaggregatethenapowerbroomwillbeprovidedtoremovethematerialsandcleantheareabeforeapplicationofprimecoat.
•Theprimecoatwillbesprayedbywell-equippedmechanicalpumpandmechanicaldistributorfixedwithatanker(truck).Blottermaterialwillbespreadfromtrucksoperatedbackwardsothatthewheelswillnottravelinuncoveredwetasphalticmaterial.Whenapplyingblottermaterialtoanasphalttreatedlanethatadjoinsalanethathasnotbeentreated,astripatleast200mmwidealongtheadjoiningedgewillbeleft.
•Theprimecoatwillbeappliedto1/2oftheroadwidthatatimeandgetaslightoverlapofasphaltmaterialalongadjoiningedgesofthelanes.Thickpaperwillbeusedtoprotectthepreviousapplicationjointsandotherappurtenances.
•Trafficwillnotbepermittedontheprimedsurfacesoonthan48hoursaftersprayofprimecoat.
•Asphaltmixwillbenotpermittedsoonerthan2hoursafterapplicationofprimecoatmaterial.Ifthereisanyexcessiveblottermaterial,dirtorotherobjectionablematerials,thesurfaceirregularitieswillbecorrectedbeforetheapplicationoftheasphaltmix.
7.7.2SupplyandLayingofBaseCourse:
•TheAsphaltBCType-1willbeusedasBase-coursewhichwillbemixaccordingtoQCSinafullycomputerizedAsphaltMixplant.AsphaltMixplantshallbeapprovedbyS