Agreement for Guaranteed Maximum Price Construction Services最高额担保建筑服务合同docx.docx
《Agreement for Guaranteed Maximum Price Construction Services最高额担保建筑服务合同docx.docx》由会员分享,可在线阅读,更多相关《Agreement for Guaranteed Maximum Price Construction Services最高额担保建筑服务合同docx.docx(161页珍藏版)》请在冰豆网上搜索。
AgreementforGuaranteedMaximumPriceConstructionServices最高额担保建筑服务合同docx
AgreementforGuaranteedMaximumPriceConstructionServices最高额担保建筑服务合同
AGREEMENT
FOR
GUARANTEEDMAXIMUMPRICE
CONSTRUCTIONSERVICES
BETWEEN
AAA,LLC
("Owner")
AND
BBB,INC.
("Contractor")
FOR
LER¨ºVE
TABLEOFCONTENTS
ARTICLEI.DEFINITIONS
1.1Architect.
1.2Change,ChangeOrder,ChangeProposalandConstructionChangeDirective.
1.3Claim
1.4Contract
1.5ContractDocuments
1.6ContractTime
1.7CostoftheWork
1.8Drawings
1.9FinalCompletion
1.10GuaranteedDateofSubstantialCompletion
1.11GuaranteedMaximumPrice
1.12MajorPermits.
1.13Modification
1.14Owner'sLenders
1.15PrincipalInteriorDesigner.
1.16Specifications.
1.17Subcontractor.
1.18SubstantialCompletion
1.19Substitution
1.20Vendor.
1.21Work
ARTICLEII.INTENT,INTERPRETATIONANDCORRELATION
2.1IntentoftheContractDocuments
2.2OrderofPrecedence.
2.3Contractor'sCompliancewithContractDocuments.
ARTICLEIII.GUARANTEEDMAXIMUMPRICE
3.1GuaranteedMaximumPrice
3.2CostoftheWork
3.3Non-AllowableCostoftheWork
3.4Contractor'sResponsibilityForTaxes.
3.5Discounts,RebatesandRefunds.
3.6NoDuplication.
ARTICLEIV.CONTRACTTIMEANDINTERIMMILESTONEDATES
4.1Definitions.
4.2TimeoftheEssence.
4.3CompletionGuarantees
4.4LiquidatedDamages.
4.5EarlyCompletion.
4.6GuarantyofCompletionandPerformance,andFinancialInformation
ARTICLEV.PAYMENTSTOCONTRACTOR
5.1ScheduleofValues
5.2ApplicationsForProgressPayments.
5.3TimeofPayments
5.4Owner'sRightToWithhold
5.5JointPayeeChecks.
5.6Retention
5.7SubstantialCompletionPayment
5.8FinalPayment
5.9DisputedPayments.
5.10OwnershipofMaterials.
5.11DepositsandPayments.
5.12Waiver.
5.13MaterialsOff-Site.
ARTICLEVI.OWNER'SRESPONSIBILITIES
6.1InformationandServices
6.2Limitations
6.3ProjectRepresentative
6.4ApprovalofMajorPurchases
6.5SiteAccess
6.6Payments
6.7ProofofFunding
6.8GoodFaith
6.9TimelyDeliveryofDrawings.
ARTICLEVII.CONTRACTOR'SRESPONSIBILITIES
7.1Contractor'sSpecificRepresentations
7.2GeneralDescription
7.3PreconstructionServices
7.4SystemsandProcedures
7.5ScheduleMeetingsandRecords
7.6Contractor'sOperations
7.7SiteDiscipline
7.8SiteSecurity
7.9CoordinationWithOthers
7.10ProductandDesignSubstitutions
7.11TestsandInspections
7.12AccesstoStoredMaterial
7.13ShopDrawings,ProductDataandSamples
7.14ProjectRecordDocumentsandAs-BuiltRequirements
7.15SiteCleanUp
7.16ConstructionFacilitiesandTemporaryControls
7.17CuttingandPatchingofWork
7.18PerformanceandPaymentBondRequirements
7.19Liens.
7.20RoyaltiesandPatents
7.21Training
7.22ConstructionPhotographs
7.23StatementofUnpaidClaims
ARTICLEVIII.ARCHITECT
8.1Architect'sAdministrationoftheContract
ARTICLEIX.SUBCONTRACTORSANDVENDORS
9.1SubcontractorsandVendors
9.2ConsentToUseProposedSubcontractorsandVendors.
9.3FormofSubcontractsandPurchaseOrders
9.4SubcontractorsandVendorsDesignatedByOwner
9.5PaymentstoSubcontractorsfromtheContractor
9.6SubcontractorandVendorReplacements
9.7CommunicationsWithSubcontractorsandVendors
9.8Assignment
ARTICLEX.WARRANTYOBLIGATIONS
10.1Contractor'sWarranty
10.2Contractor'sWarrantyPeriod
10.3ComplianceWithContractDocuments
10.4WarrantyCosts
10.5TimelinessofCorrectiveServices
10.6WarrantySurvival
10.7Owner'sRightToCorrect
10.8Owner'sRighttoSupplementWorkofContractor
10.9AcceptanceofNon-ConformingWork
10.10WarrantyExclusions
10.11WrittenGuaranty
ARTICLEXI.SCHEDULING,DELAYSANDACCELERATION
11.1Owner'sRighttoModify
11.2ProjectSchedule
11.3ScheduleUpdates
11.4ForceMajeureDelay
11.5OwnerDelay
11.6ExtensionsofTimeandGuaranteedMaximumPriceIncreasesforDelay.
11.7Limitations
11.8RecoveryPlans
11.9AccelerationsforOwner'sConvenience
11.10ScheduleCoordination
11.11Flow-DownProvisions
11.12PartialOccupancyOrUse
11.13Other
ARTICLEXII.SUBSTANTIALANDFINALCOMPLETION
12.1SubstantialCompletionProceduresandRequirements
12.2FinalCompletionProceduresandRequirements
ARTICLEXIII.CONCEALEDCONDITIONSANDUNCOVERINGOFWORK
13.1ConcealedConditions
13.2CoveringofWork
ARTICLEXIV.INDEMNIFICATION
14.1Indemnity
14.2DefenseCosts
14.3HazardousMaterials
14.4OtherLimitations
14.5SurvivalofIndemnificationProvisions
14.6Risk
ARTICLEXV.INSURANCE
15.1OwnerControlledInsuranceProgram
15.2EvidenceofCoverage
15.3Deductibles
15.4CooperationbytheParties
15.5Duration
ARTICLEXVI.SAFETYANDCOMPLIANCE
16.1Contractor'sSiteSafetyResponsibilities
16.2Compliance
ARTICLEXVII.TERMINATIONORSUSPENSIONOFTHECONTRACT
17.1MaterialDefaultByContractor
17.2TerminationForConvenience
17.3SuspensionsByOwner
17.4Limitations
17.5OtherRightsandRemedies
17.6Contractor'sRemedies
ARTICLEXVIII.CHANGEINTHEWORK
18.1Change
18.2ChangeOrder
18.3ChangeProposalRequest
18.4ConstructionChangeDirective
18.5DeterminationofIncreasesinGuaranteedMaximumPrice
18.6SimultaneousSubmittalRequirements
18.7ContinuedPerformance
18.8EffectofChangeOrders
18.9VerbalInstructionsandMinorChangesintheWork
18.10WaiverandReleaseofContractor'sRights
ARTICLEXIX.RECORDKEEPINGANDAUDITRIGHTS
19.1RequiredAccountingRecords.
19.2PurposeandExtentofRecordAccess
19.3RecordKeepingFormats
19.4Certifications.
19.5FlowDownProvisions
19.6Remedies
19.7RecordRetention.
ARTICLEXX.CLAIMS
20.1Definition
20.2Notice
20.3PendingResolution
20.4FinalSettlementofClaims
20.5UnresolvedClaims
ARTICLEXXI.OWNER'SLENDERS
21.1Owner'sLenders
21.2AssignmentandDefault
21.3Owner'sLendersElection.
21.4PaymentandWorkContinuation
21.5Payments.
21.6AuditRights.
21.7Access.
21.8MaterialChanges.
21.9GeneralCooperation.
ARTICLEXXII.DISPUTERESOLUTIONANDGOVERNINGLAW
22.1JudicialDetermination
22.2GoverningLaw
22.3Non-Waiver
22.4Severability
ARTICLEXXIII.PROPRIETARYINFORMATIONANDUSEOFOWNER'SNAME
23.1ProprietaryInformation
23.2AdvertisingandUseofOwner'sName
23.3UseofDrawings
ARTICLEXXIV.MISCELLANEOUSPROVISIONS
24.1Assignment.
24.2Subordination
24.3NoThird-PartyBeneficiaries.
24.4Enforceability.
24.5Headings.
24.6Counterparts.
24.7LegalFees.
24.8Waiver.
24.9IntentoftheParties
24.10Survival.
24.11IndependentContractor.
24.12PrivilegedBusiness.
24.13EntireAgreement
ARTICLEXXV.NOTICES
25.1NoticeProcedures
25.2NoticesToOwner
25.3NoticesToContractor
25.4ChangeofAddress.
AGREEMENTFORGUARANTEEDMAXIMUMPRICECONSTRUCTIONSERVICESLER¨ºVE
ThisAgreementforGuaranteedMaximumPriceConstructionServices("Agreement"),effectiveasof_________,_________,_________(M,D,Y)(the"EffectiveDate")isenteredintobetweenAAALLC,a_________(PLACENAME)limitedliabilitycompany("Owner"),andBBB,INC.,a_________(PLACENAME)Corporation("Contractor"),withregardtothefollowing.
RECITALS
A.Ownerownstherealpropertycommonlyknownas3131_________(PLACENAME)BoulevardSouth,_________(PLACENAME)andmoreparticularlydescribedonExhibitAattachedheretoandincorporatedhereinbythereference("Site").
B.OwnerdesirestoconstructontheSiteafirstclassluxuryresortandcasino,includinghigh-risehotelspaceandlowrisespacecomprisedofcasinoandgamingareas,restaurants,retail,conventionandmeetingareas,an"AquaTheatre"showroom,andexteriorfeatures,andallon-Siteandoff-Siteimprovementsandinfrastructurerelatedthereto,allinfullaccordancewiththeContractDocuments,includingtheDrawingsandSpecifications,andincludingtheWork(asdefinedbelow)(the"Project").Contractor'sWorkisonlyaportionoftheProject.TheProjectalsoincludesservicesandmaterialstobeprovidedbyOwnerandotherseparatecontractorsandconsultants.
C.ContractorandOwneracknowledgethattheDrawingsandSpecificationsarenotcomplete,andContractorandOwneragreetoworktogethertocompletetheDrawingsandSpecificationsasprovidedinthisAgreement,includingconsistentwiththeGuaranteedMaximumPricePremisesandAssumptionsandProjectSchedule.
D.OwnerdesirestoengageContractortoconstruct,andsupervisetheconstructionof,thatportionoftheProjectcomprisingtheWorkasmorefullydescribedinthisAgreement,andContractordesirestoacceptsuchengagement,uponthetermsandconditionscontainedinthisAgreement.
AGREEMENT
Inconsiderationofthemutualcovenantsandagreementssetforthbelow,andforothergoodandvaluableconsideration,thereceiptandsufficiencyofwhichareherebyacknowledged,ContractorandOwnerherebyadoptandincorporatetheforegoingRecitalsandagreeasfollows:
ARTICLEI.
DEFINITIONS
1.1Architect.The"Architect"fortheProjectisIII,Ltd.,LLC.oranyotherarchitectdesignatedbyOwnertoContractorinwriting;provided,however,solelywithregardtotheAquaTheatre,thetermArchitectshallmean_________(NAME),Chtd.pursuanttothatcertainProfessionalDesignServicesAgreementdatedas_________,_________,_________(M,D,Y).
1.2Change,ChangeOrder,ChangeProposalandConstructionChangeDirective.ThetermsChange,ChangeOrder,ChangeProposalandConstructionChangeDirectivearedefinedinArticle18ofthisAgreement.
1.3Claim.ThetermClaimisdefinedinSection20.1ofthisAgreement.
1.4Contract.CollectivelytheContractDocumentsdescribedinSection1.5belowformtheentirecontractforimplementationoftheWorkandarecollectivelyreferredtoasthe"Contract".
1.5ContractDocuments."ContractDocumen